Close

Articles Posted in Mechanic’s Liens

Updated:

Discharging a Mechanic’s Lien: Substance Over Form

When a subcontractor files a mechanic’s lien against a property, pursuant to Lien Law Section 19(6), the owner or any other party in interest (i.e., a general contractor), may apply for an order summarily discharging of record the alleged lien. In conjunction with the Lien Law, CPLR 402 states that…

Updated:

Executive Order Tolling the Statute of Limitations Cannot Serve to Revive a Mechanic’s Lien That Was Not Timely Renewed

It is often stated that the Lien Law is to be “liberally construed” so as to protect the rights of the contractors and workers who are the beneficiaries of the statutory scheme. However, certain rules are strictly enforced by the courts, and a failure to follow the strictures of aspects…

Updated:

Damages for Willfully Exaggerated Mechanic’s Liens Unavailable for Mechanic’s Liens that Are Prohibited by Enforceable Agreements

The Second Department recently found, in Degraw Construction Group, Inc. v. McGowan Builders, Inc., 178 A.D.3d 770, 114 N.Y.S.3d 395 (2d Dep’t 2019), that a lienor cannot be held liable for willfully exaggerating a mechanic’s lien if the mechanic’s lien is impermissible in the first place. DeGraw confirms that Lien…

Updated:

The Challenge of Proving Willful Exaggeration Under The Lien Law

In J. T. Magen & Co., Inc. v. Nissan North America, Inc., 178 A.D.3d 466 (First Dep’t 2019), the court applied some basic principles concerning willful exaggeration under the Lien Law to an unusual set of facts.  While the court did not explicitly refer to Lien Law Section 39, it…

Updated:

Second Department Upholds Mechanic’s Lien for Pre-Construction Services

The New York Lien Law provides broad categories for the type of work, labor, or services for which a contractor can file a mechanic’s lien if it is not paid. Owner’s typically argue that a contractor, construction manager, or design professional which perform preconstruction services cannot file a mechanic’s lien…

Updated:

Mechanic’s Lien Claim Not Limited By Amounts Contained In Requisitions Submitted to Owner

Contractor’s mechanic’s liens are based upon work actually performed (and unpaid). Often, contractors rely upon the payment requisitions they submitted to the owner to establish the claimed value of the work. Requisitions that were never submitted to or considered by an owner can also be used by a contractor on…

Updated:

The Court of Appeals Upholds the Fourth Department’s Lien Law Section 3 Consent Decision

On November 20, 2018, in Angelo A. Ferrara v. Peaches Café LLC, et al., 2018 WL 6047993 (N.Y. Nov. 20, 2018), the New York Court of Appeals upheld the Fourth Department’s decision in Ferrera v. Peaches Café LLC, 138 A.D.3d 1391, 30 N.Y.S.3d 765 (4th Dep’t 2016). As I discussed in my prior…

Updated:

The Divide in Interpretations of Lien Law Section 3’s Consent Requirement Continues

As I previously noted in my post titled “Varying Interpretations of Lien Law Section 3’s Consent Requirement,” last year the New York Court of Appeals granted a motion for leave to appeal the Fourth Department’s decision in Ferrera v. Peaches Café LLC, 138 A.D.3d 1391, 30 N.Y.S.3d 765 (4th Dep’t…

Updated:

Lienor Unable To Establish Lien Fund Based Upon Owner’s Alleged “Bad Faith” Payment

Enforcing mechanic’s lien rights raises several issues which are distinct from the ability to simply file a mechanic’s lien. For example, a subcontractor must generally show that a “lien fund” existed between the owner and contractor at the time it filed its lien in order to successfully foreclose. Peri Formwork…

Contact Us