Articles Tagged with consent

As I previously noted in my post titled “Varying Interpretations of Lien Law Section 3’s Consent Requirement,” last year the New York Court of Appeals granted a motion for leave to appeal the Fourth Department’s decision in Ferrera v. Peaches Café LLC, 138 A.D.3d 1391, 30 N.Y.S.3d 765 (4th Dep’t 2016). The appeal was argued during the week of October 16, 2018, but the Court of Appeals has not yet issued a decision.

Lien Law Section 3 provides that a contractor “who performs labor or furnishes materials for the improvement of real property with the consent or at the request of the owner thereof … shall have a lien … upon the real property improved.” In the underlying Peaches case, the Fourth Department compared First, Second and Third Department decisions concerning Lien Law Section 3’s consent requirement, all of which found, at various times, “that a lien under Lien Law Section 3 is valid only when the property owner directly authorizes the contractor to undertake the relevant improvements.” Peaches, 30 N.Y.S.3d at 768 (emphasis added). The Fourth Department, however, concluded that “consent” should be broadly interpreted because the decisions of its sister departments could not be “squared” with Jones v. Menke, 168 N.Y. 61 (1901) or McNulty Bros. v. Offerman et al., 221 N.Y. 98 (1917), two Court of Appeals cases which have not been “overturned or disavowed.” Id. at 767-8.

In both Jones and McNulty, the Court of Appeals found, generally, that contractual obligations requiring a tenant to make certain improvements to the premises satisfied the consent requirement of Lien Law Section 3.  Id. at 676. As a result, the lien claims in those cases were permitted against the underlying owner’s property. Id. Accordingly, in Peaches, the Fourth Department determined that the owner’s consent could be implied by the terms of the subject lease, even though the owner did not provide direct consent to the contractor.

Last September, the New York Court of Appeals granted a motion for leave to appeal the Fourth Department’s decision in Ferrera v. Peaches Café LLC, 138 A.D.3d 1391, 30 N.Y.S.3d 765 (4th Dep’t 2016). In Peaches, the Fourth Department enforced a mechanic’s lien filed by a contractor who was hired by a tenant and had no direct relationship with the landlord/owner. However, if this same mechanic’s lien had been filed against real property governed by any other New York Appellate Department, the mechanic’s lien would have very likely been discharged.

Lien Law Section 3 states that a contractor “who performs labor or furnishes materials for the improvement of real property with the consent or at the request of the owner thereof … shall have a lien for the principal and interest, of the value, or the agreed price, of such labor ….”

The First, Second and Third Departments have determined that in order for a mechanic’s lien to come within Lien Law Section 3, the owner must be an affirmative factor in procuring the improvement, or else, having possession and control of the premises, assent to the improvement in the expectation that he will reap the benefit of it. See Paul Mock, Inc. v. 118 East 25th Street Realty Co., 87 A.D.2d 756, 448 N.Y.S.2d 693 (1st Dep’t 1982); Interior Bldg. Services, Inc. v. Broadway 1384 LLC, 73 A.D.3d 529, 900 N.Y.S.2d 311 (1st Dep’t 2010); Matell Contracting Co., Inc. v. Fleetwood Park Development, LLC, 111 A.D.3d 681, 974 N.Y.S.2d 573 (2d Dep’t 2013); Drapaniotis v. 36-08 33rd Street Corp., 48 A.D. 3d 736, 853 N.Y.S.2d 356 (2d Dep’t 2008; Sager v. Renwick Park & Traffic Assn., 172 A.D. 359, 159 N.Y.S. 4 (3d Dep’t 1916).